Under development

Talasol - Spain PV (300 MW) 

Talasol is promoting the construction of a photovoltaic plant with a peak capacity of 300 MW in the municipality of Talaván, Cáceres, Spain (the “Talasol Project”). Ellomay acquired Talasol’s shares in April 2017 for an aggregate consideration of Euro 10 million (with Euro 2 million held in escrow).

In April 2019 Ellomay sold an aggregate of 49% of the outstanding shares of Talasol for an aggregate purchase price of approximately Euro 16.1 million. Accordingly, Ellomay owns 51% of Talasol.

During June 2018, Talasol entered into an engineering, procurement & construction agreement (the “EPC Agreement”) with METKA EGN Limited (“METKA EGN”). The EPC Agreement provides a fixed and lump-sum amount of Euro 192.5 million for the complete execution and performance of the works defined in the EPC Agreement. The works include the engineering, procurement and construction of the Talasol Project and the ancillary facilities for injecting power into the grid, including a 400 kV step-up substation, the high voltage interconnection line to the point of connection to the grid and performance of two years of O&M services. METKA EGN is expected to complete the works under the EPC Agreement in Q3 2020.

In June 2018, Talasol executed a financial power swap in respect of approximately 80% of the output of a prospective photovoltaic plant for a period of 10 years (the “PPA”). The PPA was executed with a leading international energy company with a solid investment grade credit rating and a pan-European asset base, which is active in more than 40 countries and has a proven track record in financial hedges. The power produced by the Talasol Project is expected to be sold in the open market for the then current market power price and the PPA hedges the risks associated with fluctuating electricity market prices by allowing Talasol to secure a stable income for the power production included under the PPA.

In December 2018, Talasol entered into a set of agreements governing the procurement of financing for the development and construction of the Talasol Project in the aggregate amount of approximately Euro 177 million (the “Project Finance”). The Project Finance is led by Deutsche Bank, which is the mandated lead arranger, and the European Investment Bank (EIB). . The Talasol Project reached financial closing on April 30, 2019.

Based on current technical analysis of the design provided by the EPC contractor of the Talasol Project, the P50 expected production of the Talasol Project is approximately 561 GWh per annum. It is expected that the Talasol Project’s CAPEX will amount to approximately Euro 200-230 million, including development costs of approximately Euro 20 million and interest of approximately Euro 7 million. Based on the current technical analysis, a price projection analysis and the expected hedging effect of the PPA, the Talasol Project’s revenues are currently expected to be in the range of Euro 23-25 million per annum. The expected operation expenses are Euro 6 million per annum, thus the net operation income, revenues net of operation expenses, is expected to be Euro 17-19 million.

Location: Municipality of Talaván, Cáceres, Spain

Spain (28 MW)

Ellomay is promoting a PV plant with a peak capacity of 28 MW in a plot adjacent to the land on which the Talasol Project is constructed. Ellomay received a grid connection permit and executed a land lease agreement. The plant is expected to become operational during 2021.

Framework Agreements for Development of PV Projects in Italy (550 MW)

First Framework Agreement

In November 2019, Ellomay executed a Framework Agreement with an established and experienced European developer and contractor. Pursuant to this Framework Agreement, the developer will scout and develop photovoltaic greenfield projects in Italy with the aim of reaching an aggregate authorized capacity of at least 250 MW over a three-year period. 

Second Framework Agreement

In December, 2019, Ellomay executed an additional Framework Agreement with an established and experienced European developer. Pursuant to the additional Framework Agreement, the developer will provide Ellomay with development services with respect to photovoltaic greenfield projects in Italy in the scope of 350 MW with the aim of reaching an aggregate “ready to build” authorized capacity of at least 265 MW over a forty-one month period.

In addition to the 265 MW mentioned above, Ellomay Luxembourg has the option to purchase approximately 37 MW that are already under development by the developer, 30 MW of which have already received the approval for connection to the Italian electricity grid. 

There can be no assurance as to the aggregate capacity of projects that will reach the “ready to build” status, and as to our decision and success in completing construction of any of such projects.