Q3 2023

Tel-Aviv, Israel, December 31, 2023 – Ellomay Capital Ltd. (NYSE American; TASE: ELLO) (“Ellomay” or
the “Company”), a renewable energy and power generator and developer of renewable energy and power projects
in Europe, USA and Israel, today reported unaudited financial results for the three and nine month periods ended
September 30, 2023.
Financial Highlights

  • Total assets as of September 30, 2023 amounted to approximately €612.3 million, compared to total assets
    as of December 31, 2022 of approximately €576.2 million.
  • Revenues for the three months ended September 30, 2023 were approximately €15.6 million, compared to
    approximately €15.5 for the three months ended September 30, 2022. Revenues for the nine months ended
    September 30, 2023 were approximately €41.1 million, compared to approximately €44.7 million for the
    nine months ended September 30, 2022.
  • Profit for the three months ended September 30, 2023 was approximately €5.9 million, compared to a loss
    of approximately €1.7 million for the three months ended September 30, 2022. Profit for the nine months
    ended September 30, 2023 was approximately €10.4 million, compared to a loss of approximately €2.3
    million for the nine months ended September 30, 2022.
  • EBITDA for the three months ended September 30, 2023 was approximately €11.6 million, compared to
    approximately €8.6 million for the three months ended September 30, 2022. EBITDA for the nine months
    ended September 30, 2023 was approximately €21.5 million, compared to approximately €19.2 million for
    the nine months ended September 30, 2022. See below under “Use of Non-IFRS Financial Measures” for
    additional disclosure concerning EBITDA.
    Financial Overview
  • Revenues were approximately €41.1 million for the nine months ended September 30, 2023, compared to
    approximately €44.7 million for the nine months ended September 30, 2022. This decrease mainly results
    from the decrease in electricity prices in Spain and from a curtailment of the electricity supply from the
    Company’s facilities to the grid during June 2023 due to maintenance and upgrade work on the main
    transmission line between Spain and Portugal, which caused a decrease in revenues of approximately €1
    million. The Company subsequently implemented a solution aimed at minimizing the impact of future
    similar curtailments. The decrease in revenues was partially offset by an increase in revenues from the
    Company’s biogas plants in the Netherlands, resulting mainly from increased production and an increase
    in the 2023 gas price, and from the connection to the grid of Ellomay Solar (a 28 MW photovoltaic plant
    in Spain) during June 2022, upon which the Company commenced recognition of revenues.
  • Operating expenses were approximately €17.7 million for the nine months ended September 30, 2023,
    compared to approximately €18.4 million for the nine months ended September 30, 2022. This decrease
    mainly results from a decrease in payments under the Spanish RDL 17/2022, caused by a reduction in the
    electricity market price. RDL 17/2022 established the reduction of returns on the electricity generating
    activity of Spanish production facilities that do not emit greenhouse gases, accomplished through payments
    of a portion of the revenues by the production facilities to the Spanish government. As a result of the
    decrease in the electricity market price in Spain during the nine months ended September 30, 2023, the
    payments under RDL 17/2022 were lower during this period compared to the same period last year. This
    decrease in operating expenses was partially offset by increased operating expenses in connection with the
    Company’s biogas operations in the Netherlands caused by the use of higher quality raw materials due to
    lower availability of cheaper raw materials, and from the connection to the grid of Ellomay Solar during
    June 2022, upon which the Company commenced recognition of expenses. Depreciation expenses were
    approximately €12 million for the nine months ended September 30, 2023, compared to approximately
    €11.9 million for the nine months ended September 30, 2022.
    2
  • Project development costs were approximately €2.4 million for the nine months ended September 30, 2023,
    compared to approximately €2.7 million for the nine months ended September 30, 2022. The decrease in
    project development costs is mainly due to projects in the United States and Italy that reached “ready to
    build” status, which results in the commencement of the capitalization of expenses related to such projects
    into fixed assets.
  • General and administrative expenses were approximately €4.1 million for the nine months ended September
    30, 2023, compared to approximately €5 million for the nine months ended September 30, 2022. The
    decrease in general and administrative expenses is mostly due to a decrease in D&O liability insurance
    costs and to bonuses paid to employees in 2022.
  • Share of profits of equity accounted investee, after elimination of intercompany transactions, was
    approximately €4.6 million for the nine months ended September 30, 2023, compared to approximately
    €0.6 million for the nine months ended September 30, 2022. The increase in share of profits of equity
    accounted investee was mainly due to the increase in revenues of Dorad Energy Ltd. (“Dorad”) due to
    higher quantities produced and a higher electricity tariff in Israel, partially offset by an increase in operating
    expenses in connection with the increased production and higher tariff.
  • Financing income, net was approximately €0.6 million for the nine months ended September 30, 2023,
    compared to financing expenses, net of approximately €7.7 million for the nine months ended September
    30, 2022. The change was mainly attributable to income resulting from exchange rate differences
    amounting to approximately €8 million in the nine months ended September 30, 2023, mainly in connection
    with the New Israeli Shekel (“NIS”) cash and cash equivalents and the Company’s NIS denominated
    debentures, compared to expenses in the amount of approximately €1 million for the nine months ended
    September 30, 2022, caused by the 8% appreciation of the euro against the NIS during the nine months
    ended September 30, 2023, compared to the 1% devaluation of the euro against the NIS during the nine
    months ended September 30, 2022.
  • Tax benefit was approximately €0.5 million for the nine months ended September 30, 2023, compared to
    taxes on income of approximately €2 million for the nine months ended September 30, 2022.
  • Profit for the nine months ended September 30, 2023 was approximately €10.4 million, compared to a loss
    of approximately €2.3 million for the nine months ended September 30, 2022.
  • Total other comprehensive income was approximately €31.6 million for the nine months ended September
    30, 2023, compared to total other comprehensive loss of approximately €61.8 million for the nine months
    ended September 30, 2022. The change mainly resulted from changes in fair value of cash flow hedges,
    including a material increase in the fair value of the financial power swap (the “Talasol PPA”) that covers
    approximately 80% of the output of the Talasol PV Plant compared to the same period last year. The Talasol
    PPA experienced a high volatility due to the significant changes in electricity prices in Europe that included
    a substantial increase in prices during 2021 and 2022 and a substantial decrease in prices during 2023. In
    accordance with hedge accounting standards, the changes in the Talasol PPA’s fair value are recorded in
    the Company’s shareholders’ equity through a hedging reserve and not through the accumulated
    deficit/retained earnings. The changes do not impact the Company’s consolidated net profit/loss or the
    Company’s consolidated cash flows. As the Company controls Talasol, the total impact of the changes in
    fair value of the Talasol PPA (including the minority share) is consolidated into the Company’s financial
    statements and total equity.
  • Total comprehensive income was approximately €42 million for the nine months ended September 30,
    2023, compared to total comprehensive loss of approximately €64.1 million for the nine months ended
    September 30, 2022.
  • Net cash provided by operating activities was approximately €16.8 million for the nine months ended
    September 30, 2023, compared to approximately €14 million for the nine months ended September 30,
  1. The increase in net cash provided by operating activities for the nine months ended September 30,
    2023, is mainly due to payment of interest from Dorad and to the 8% appreciation of the euro against the
    NIS during the nine months ended September 30, 2023 that impacted our NIS-denominated cash and cash
    equivalents.
    3
  • On October 7, 2023, the “Iron Swards” war broke out in Israel following an attack in Southern Israel by
    Hamas. The war and hostilities, including missile attacks, mainly on southern and northern Israel, have
    continued since then. The substantial majority of the Company’s operating facilities, which serve as the
    Company’s main sources of liquidity, are located outside of Israel, in Spain and the Netherlands. The
    substantial majority of the projects under development of the Company are also located outside of Israel,
    in Italy, the US and Spain. These facilities and projects were not impacted by the war and hostilities in
    Israel. The Company’s headquarters are located in Tel Aviv, which is in central Israel, and the Company’s
    headquarter work continued uninterrupted throughout the war and hostilities.
    The Company has three assets that are currently operating or under construction in Israel: (i) the Talmei
    Yosef PV Facility (100% owned by the Company, in southern Israel), (ii) the Pumped Storage Project in
    the Manara Cliff (83.34% owned by the Company, in northern Israel), and (iii) the Dorad power plant
    (9.375% owned by the Company, in southern Israel). As previously published by the Company, the
    construction works on the Manara site stopped in early October 2023 and the contractor is using this period
    in which construction is halted to continue the planning work and advancing the project. The Company
    expects to receive compensation for the delays through the fees that will be paid for the electricity and
    availability after the project becomes operational and through direct compensation for damages. The Talmei
    Yosef facility and the Dorad power plant have not been materially impacted by the war and are currently
    fully operational. The continuation or future escalation of the war and hostilities in southern and northern
    Israel, including potential direct damage due to missile attacks, temporary or permanents cessation of
    operations and potential inability to access the sites, could materially adversely impact the Company’s
    Israeli operations and projects under development and the Company’s results of operations.
    CEO Review Third Quarter 2023
    The first nine months of 2023 were characterized by a decline in the electricity prices in Europe compared
    to 2022. The decrease is mainly evident in Spain, whereas in Italy the prices remained stable. Despite the
    decrease in electricity prices in Spain, the EBITDA for the period increased by approximately €2.3 million
    compared to the same period last year, and amounted to approximately €21.5 million. The Dorad power
    station showed an increase in revenues and net income and this trend is expected to continue also during
    next year. The development activities of solar projects in the USA is continuing and their construction is
    expected to commence in the beginning of 2024. In Italy, the construction of a solar project with a capacity
    of 18 MW commenced, in addition to solar projects with a capacity of 20 MW whose construction finished
    and they are awaiting connection to the grid.
    The Company’s operations concentrate on three main fields:
  • Construction of New Projects: solar projects in the USA (land preparation works are complete), solar projects
    in Italy, and a pumped hydro storage project in the Manara Cliff in Israel.
  • Initiating and Developing of New Projects: solar projects in Italy, Spain, USA and Israel.
  • Management, Operation and Improvement of Generating Projects: in Israel (solar), Spain (solar) and the
    Netherlands (bio-gas).
    The Company’s revenues for the quarter were approximately €15.6 million, a small decrease compared to the same
    period last year, despite the decrease in electricity prices compared to the same period last year. The operating profit
    increased by approximately €3 million, mainly as a result of the increase in Dorad’s profit.
    The net profit for the third quarter of 2023 was approximately €5.9 million and the net profit for the first nine
    months of 2023 was approximately €10.5 million.
    Activity in Spain:
    The Talasol solar project (300 solar MW) (Company’s share is 51%) produced during the third quarter revenues
    from the sale of electricity and green certificates of approximately €8.9 million. Talasol is a party to a financial
    hedge of its electricity capture price (PPA). Approximately 80% of its production (75% based on P-50) are sold
    under this agreement for a fixed price. The remaining electricity produced by Talasol is sold directly to the grid, at
    spot prices.
    The Ellomay Solar project (28 solar MW) produced during the third quarter of 2023 revenues from the sale of
    electricity and green certificates of approximately €1.5 million.
    4
    Activity in Italy:
    The Company has approximately 505 solar MW projects under advanced development stages, of which licenses
    have been obtained for approximately 203 MW. Projects with an aggregate capacity of 20 MW are expected to be
    connected to the grid during the coming month. Preliminary construction works in projects with an aggregate
    capacity of approximately 105 MW commenced during the third quarter of 2023 and construction works in the
    remainder of the licenses (approximately 78 MW) are expected to commence in early 2024.
    The Company has additional projects in early development stages (in addition to the 505 MW in advanced
    development stages), the intention of the Company is to reach a portfolio of approximately 1,000 solar MW by the
    end of 2026.
    Activity in Israel:
    The Manara Pumped Storage Project (Company’s share is 83.34%): The Manara Cliff pumped storage project,
    with a capacity of 156 MW, is in advanced construction stages. The Iron Swards War, which commenced on
    October 7, 2023, stopped the construction works on the project. The project has full protection for damages and
    losses due to the war within the framework of covenants that support financing provided by the Israeli state as part
    of the tariff regulation. The project is expected to reach commercial operation during the first half of 2027, and to
    produce average annual revenues of approximately €74 million and EBITDA of approximately €33 million.
    1 The
    Company and its partner in the project, Ampa, invested the equity required for the project (other than
    linkage differences), and the remainder of the funding is from a consortium of lenders led by Mizrahi Bank, at a
    scope of approximately NIS 1.18 billion.
    Development of Solar licenses combined with storage:
    Projects no. 1 and 2 are based on tender No. 1 that the Company won and there is an option of transition to regulation
    that enables a direct sale to end customers.
  1. The Komemiyut Project: intended for 21 solar MW and 47 MW / hour batteries. The project has an approval
    for connection to the grid and is in the process of receiving a building permit. Commencement of construction
    is planned for the first quarter of 2024.
  2. The Qelahim Project: intended for 15 solar MW and 33 MW / hour batteries. The project has an approval for
    connection to the grid, and is in the final stages of the zoning approval.
  3. The Talmei Yosef Project: an expansion of the existing project to 104 dunams, intended for 10 solar MW
    and 22 MW / hour batteries. The request for zoning approval was approved in the fourth quarter of 2023.
  4. The Talmei Yosef Storage Project in Batteries: there is a zoning approval for 30 dunam, intended for
    approximately 400 MW / hour. The project is designed for the regulation of high voltage storage.
  5. In addition, the Company has approximately 46 solar MW under preliminary planning stages.
    Dorad Power Station (Company’s share is approximately 9.4%): the gas flow from the Karish reservoir that began
    in November 2022 reduced the gas costs of Dorad. Dorad benefited from the increase in the TAOZ and the
    production component compared to the same period last year. In addition, the Israeli Electricity Authority’s
    resolution in connection with the changes of the hourly tariffs, which entered into force in January 2023, means an
    extension of the “summer” period (a month was added to the “summer” season in which the tariffs are higher), the
    elimination of the “GEVA” (average consumption) hours and the change in the “PISGA” (peak) hours in the
    intermediate seasons to the afternoon and evening. As a result, Dorad provides availability to the system manager
    for the “SHEFEL” (low) period, which is longer and the demand of the system manager is higher. As a result of the
    continuous operations of the power plant, the maintenance expenses decreased and the hours of operation increased,
    increasing production and the revenues and profit. Moreover, the Israeli government decided to increase the power
    1
    EBITDA is a non-IFRS measure. The Company is unable to provide a reconciliation of the Manara Project’s EBITDA to the
    Manara Project’s net profit/loss on a forward-looking basis without unreasonable effort because items that impact this IFRS
    financial measure are not within the Company’s control and/or cannot be reasonably predicted. These items include, among
    others, exchange rate fluctuations, depreciation and amortization, other income, finance income, finance expenses and taxes
    on income. Such items may have a significant impact on the future financial results and the Company believes such a
    reconciliation for the projected results will not be meaningful.
    5
    station by an additional 650 MW and the National Infrastructure Committee approved the TTL/11/B plan –
    expansion of the Dorad power station.
    In June 2023, an arbitration award was given that, among other issues, obligated Zorlu and Edeltech to refund
    approximately $130 million to Dorad and to pay the derivative plaintiffs NIS 20 million as reimbursement of legal
    expenses. Appeals on the arbitration award were submitted by both parties and the appeal process was agreed in
    advance and is expected to end in the first quarter of 2024.
    Activity in the Netherlands:
    In connection with the military conflict in Ukraine and the stoppage of Russian gas supply to Europe, there are
    substantial changes in the field of biogas in the Netherlands and Europe. Europe in general and the Netherlands
    specifically have set ambitious goals for increasing gas production from waste. Various incentives are being
    considered, the main one is increasing the price of the green certificates. The price of these certificates has increased
    from approximately 13–15 euro cents per cubic meter to around 45 euro cents per cubic meter. The prices of greed
    certificates continue to rise and the expectation is that the price will reach approximately 60 euro cents per cubic
    meter in 2024.
    The Company estimates that with the increasing importance of the biogas field, this field entered into a new era. In
    the Netherlands, new legislation was adopted that obliges the gas suppliers to incorporate green gas in a scope of
    up to 20% of the amount supplied by them, valid commencing January 1, 2025. This legislation and the growing
    demand for green certificates derived from the biogas industry, is expected to add and significantly improve the
    results of the biogas segment of the Company.
    Activity in Texas, USA:
    The Company executed a joint development agreement for the development of solar projects in the State of Texas,
    USA. The agreement covers an initial two projects, with an aggregate installed capacity of 26 MW DC, and an
    option for two additional projects under similar terms with an aggregate installed capacity of 20 MW DC. The first
    two projects have reached ready-to-build status, commencement of construction is expected in the beginning of
    2024 and they are expected to be constructed within 8-10 months. One of the two additional projects has also
    reached ready-to-build status and the other additional project is expected to achieve ready-to-build status during the
    first quarter of 2024. It is expected that the two additional projects will be constructed during the second half of
  6. The estimated capital cost for the first two projects is $30-$32 million, of which the Company’s share is
    expected to be approximately $19-$21 million. The estimated capital cost for the two additional projects is $24-$26
    million, of which the Company’s share is expected to be $15-$17 million. The remaining capital costs are expected
    to be covered by tax equity partners.
    Use of Non-IFRS Financial Measures
    EBITDA is a non-IFRS measure and is defined as earnings before financial expenses, net, taxes, depreciation and
    amortization. The Company presents this measure in order to enhance the understanding of the Company’s
    operating performance and to enable comparability between periods. While the Company considers EBITDA to be
    an important measure of comparative operating performance, EBITDA should not be considered in isolation or as
    a substitute for net income or other statement of operations or cash flow data prepared in accordance with IFRS as
    a measure of profitability or liquidity. EBITDA does not take into account the Company’s commitments, including
    capital expenditures and restricted cash and, accordingly, is not necessarily indicative of amounts that may be
    available for discretionary uses. Not all companies calculate EBITDA in the same manner, and the measure as
    presented may not be comparable to similarly-titled measure presented by other companies. The Company’s
    EBITDA may not be indicative of the Company’s historic operating results; nor is it meant to be predictive of
    potential future results. The Company uses this measure internally as performance measure and believes that when
    this measure is combined with IFRS measure it add useful information concerning the Company’s operating
    performance. A reconciliation between results on an IFRS and non-IFRS basis is provided on page 14 of this press
    release.
    About Ellomay Capital Ltd.
    Ellomay is an Israeli based company whose shares are registered with the NYSE American and with the Tel Aviv
    Stock Exchange under the trading symbol “ELLO”. Since 2009, Ellomay Capital focuses its business in the
    renewable energy and power sectors in Europe, USA and Israel.
    6
    To date, Ellomay has evaluated numerous opportunities and invested significant funds in the renewable, clean
    energy and natural resources industries in Israel, Italy, Spain, The Netherlands and Texas, USA, including:
  • Approximately 35.9 MW of photovoltaic power plants in Spain and a photovoltaic power plant of
    approximately 9 MW in Israel;
  • 9.375% indirect interest in Dorad Energy Ltd., which owns and operates one of Israel’s largest private
    power plants with production capacity of approximately 850MW, representing about 6%-8% of Israel’s
    total current electricity consumption;
  • 51% of Talasol, which owns a photovoltaic plant with a peak capacity of 300MW in the municipality of
    Talaván, Cáceres, Spain;
  • Groen Gas Goor B.V., Groen Gas Oude-Tonge B.V. and Groen Gas Gelderland B.V., project companies
    operating anaerobic digestion plants in the Netherlands, with a green gas production capacity of
    approximately 3 million, 3.8 million and 9.5 million Nm3 per year, respectively;
  • 83.333% of Ellomay Pumped Storage (2014) Ltd., which is involved in a project to construct a 156 MW
    pumped storage hydro power plant in the Manara Cliff, Israel;
  • Ellomay Solar Italy One SRL and Ellomay Solar Italy Two SRL that are constructing photovoltaic plants
    with installed capacity of 14.8 MW and 4.95 MW, respectively, in the Lazio Region, Italy;
  • Ellomay Solar Italy Four SRL, Ellomay Solar Italy Five SRL, Ellomay Solar Italy Seven SRL, Ellomay
    Solar Italy Nine SRL and Ellomay Solar Italy Ten SRL that are developing photovoltaic projects with
    installed capacity of 15.06 MW, 87.2 MW, 54.77 MW, 8 MW and 18 MW, respectively, in Italy that have
    reached “ready to build” status; and
  • Fairfield Solar Project, LLC, Malakoff Solar I, LLC, Malakoff Solar II, LLC, Mexia I Solar, LLC, Mexia II
    Solar, LLC, and Talco Solar, LLC, that are developing photovoltaic projects with installed capacity of 13
    MW, 6.5 MW, 6.5 MW, 4 MW, 4 MW and 7.5 MW respectively, in the Dallas Metropolitan area, Texas,
    and have reached “ready to build” status.
    For more information about Ellomay, visit http://www.ellomay.com.
    Information Relating to Forward-Looking Statements
    This press release contains forward-looking statements that involve substantial risks and uncertainties, including
    statements that are based on the current expectations and assumptions of the Company’s management. All statements,
    other than statements of historical facts, included in this press release regarding the Company’s plans and objectives,
    expectations and assumptions of management are forward-looking statements. The use of certain words, including
    the words “estimate,” “project,” “intend,” “expect,” “believe” and similar expressions are intended to identify
    forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. The
    Company may not actually achieve the plans, intentions or expectations disclosed in the forward-looking statements
    and you should not place undue reliance on the Company’s forward-looking statements. Various important factors
    could cause actual results or events to differ materially from those that may be expressed or implied by the Company’s
    forward-looking statements, including changes in electricity prices and demand, the impact of the war and hostilities
    in Israel and Gaza, regulatory changes, including extension of current or approval of new rules and regulations
    increasing the operating expenses of manufacturers of renewable energy in Spain, increases in interest rates and
    inflation, changes in the supply and prices of resources required for the operation of the Company’s facilities (such
    as waste and natural gas) and in the price of oil, the impact of the continued military conflict between Russia and
    Ukraine, technical and other disruptions in the operations or construction of the power plants owned by the Company
    and general market, political and economic conditions in the countries in which the Company operates, including
    Israel, Spain, Italy and the United States. These and other risks and uncertainties associated with the Company’s
    business are described in greater detail in the filings the Company makes from time to time with Securities and
    Exchange Commission, including its Annual Report on Form 20-F. The forward-looking statements are made as of
    this date and the Company does not undertake any obligation to update any forward-looking statements, whether as
    a result of new information, future events or otherwise.
    Contact:
    Kalia Rubenbach (Weintraub)
    CFO
  • Tel: +972 (3) 797-1111
  • Email: hilai@ellomay.com